This article explains how to create and manage Preload Lists in ROMAC Production Control to group shipping items before creating delivery tickets.
What Is a Preload List?
A Preload List is a saved collection of shipping pieces intended to be loaded together for a jobsite delivery or transfer to an outside processor. It allows staging material before final shipment.
When to Use a Preload List
Use a preload list when:
- You want to pre-stage items for loading
- You’re building loads in multiple phases
- You need to track items going to galvanizers, painters, or subcontractors
Creating a Preload List
- Open the project
- Go to Tools > Preload List Manager
- Click New Preload List
- Enter a unique Preload ID or Name
- Add items using:
- Drawing and Piece Mark filters
- Manual selection from available shipping pieces
- Save the list
You can create multiple Preload Lists per job.
Editing and Managing Preload Lists
- Use Edit Preload to change items in the list
- Use Delete Preload to remove an unused list
- Use Copy Preload to duplicate a list as a starting point
Preload Lists are not actual shipments until assigned to a ticket.
Using Preloads in Shipping Tickets
Once a list is complete:
- Go to Shipping > Create Ticket
- Choose Use Preload List
- Select the list you created
- Complete the ticket details and print if needed
This helps ensure accurate loading and ticketing without missing items.